Capital Projects

Most of the Capital Projects relating to the improvement of our outdoor recreational facilities have been sponsored by the Recreation Department. Our objective is to have state of the art, aesthetically pleasing, functional and safe recreational facilities that meet the needs of our residents.

FY21 - FY25 Capital Improvement Plan

FY22 - FY26 Capital Improvement Plan

Recreational Facilities Capital Projects 

February 2021 Update

Arsenal Park Phase A - design plans

In construction phase - 60% complete. 

Contractor has prepared the site for winter shutdown – will continue work as weather permits. 

Anticipated project completion June 2021. 


Arsenal Park Phase B - design plans

The Planning & Development Department, in conjunction with the Conservation Committee, is overseeing Phase B renovations. 

Future public meetings will be held to finalize proposed plans. 


Casey Park Phase II – design plans

Preliminary design phase with a concept plan rendering dated February 2018

Highlights include updated baseball amenities, storage and restrooms.


Filippello Park Spray Park – design plans

Planning including site visits, coordination with local authorities and manufacturers, and determining state/local permit requirements.

Scope, schedule and budget are in development for a draft contract. 


Filippello Park Sports Field Lighting Project  - design plans

Arlington Street Lights - Complete 

Grove Street Lights - In Construction Phase

Foundation excavation began in January 2021 and was completed in February 2021. 

Lighting and fencing installation to be completed in March 2021, the new scoreboard was installed March 2, 2021.

Project has been delayed from Summer 2020 completion due to increased construction oversight required by the DEP.

Final seeding and landscaping for the soil excavate area to be completed May 2021. 


Lowell Tot Lot 

CDM Smith submitted a proposal including scope and budget for design, bidding and construction administration, status pending.


Moxley Park – design plans

Preliminary design phase with a concept plan rendering dated February 2018.

Upon review and recommendation, the development of scope, schedule, and budget will begin for a draft contract to review. 

Updated amenities will include an inline skating, tennis and basketball courts, updated baseball field features, and fencing replacements.


Saltonstall Tot Lot and Field Lighting Improvements – design plans

No Preliminary Design Phase was conducted – No Public Meetings were held 

Project design plans will be reviewed with others to determine priority in the Capital Budget planning.


Victory Field Phase II Improvements – design plans

Town Administration requested hold on further work due to potential impacts of the High School Project, project ready to continue when directed.